LNG & Cryogenic: Chile LNG

The Quintero LNG terminal initially regasified 10Mm³/d when operations begin in 2009 with a final maximum level of 15Mm³/d. The complex comprises a quay approximately 1,300m long, unloading arms, two storage tanks of around 160,000m³ capacity each, two small storage tanks of 10,000m³ capacity and a vaporisation station.

Specification

PJ Valves supplied packages containing valves for cryogenic service, and non-cryogenic valves for associated processes. The scope of supply involved managing sub-orders from our own manufacturing works, and partner factories. PJ Valves supplied Ball, DBB, Globe and Check valves in stainless steel, up to 2” in size and 900# pressure class.

Outcome

PJ Valves supplied all valves with the 28 week required delivery. This allowed our clients package to continue unimpeded and be delivered to site on schedule.

Related Project Experience
PJ Valves - Angola - LNG

PJV supplied cryogenic valves to the project for Chevron, suitable to -196degC.

PJ Valves - Chile - LNG

PJV Cryogenic valves supplied through CB&I in the UK.

PJV supplied valves through Bechtel for low temperature applications for GASCO.